This includes Mars, Jupiter, Saturn, Uranus, Neptune, Pluto, their satellites, and comets, asteroids and minor planets at or beyond the orbit of Mars. Webb has sufficient near-IR and mid-IR sensitivity to be able to observe virtually all known Kuiper Belt Objects. In addition, it can observe opportunistic and unplanned targets such as supernovae and gamma ray bursts within 48 hours of a decision to do so. with continuous orientation of its sunshield and equipment bus toward the Sun, Earth and Moon. Combined with its wide, shadow-avoiding orbit, the telescope can simultaneously block incoming heat and light from all three bodies and avoid even the most minor changes in temperature from Earth and Moon shadows that would affect the structure, while maintaining uninterrupted solar power and Earth communications on its Sun-facing side. This arrangement keeps the temperature of the spacecraft constant and below the necessary for faint infrared observations.

Sunshield protection

thumb|upright=1.4|right|Test unit of the sunshield stacked and expanded at the [[Northrop Grumman facility in California, 2014]]

To make observations in the infrared spectrum, Webb must be kept under ; otherwise, infrared radiation from the telescope itself would overwhelm its instruments. Its large sunshield blocks light and heat from the Sun, Earth, and Moon, and its position near the Sun–Earth keeps all three bodies on the same side of the spacecraft at all times. Its halo orbit around the L<sub>2</sub> point avoids the shadow of the Earth and Moon, maintaining a constant environment for the sunshield and solar arrays. Each layer is made of Kapton E film, coated with aluminum on both sides. The two outermost layers have an additional coating of doped silicon on the Sun-facing sides, to better reflect the Sun's heat into space. Accidental tears of the delicate film structure during deployment testing in 2018 led to further delays to the telescope deployment.

The sunshield was designed to be folded twelve times so that it would fit within the Ariane&nbsp;5 rocket's payload fairing, which is in diameter, and long. The shield's fully deployed dimensions were planned as .

Keeping within the shadow of the sunshield limits the field of regard of Webb at any given time. The telescope can see 40 percent of the sky from any one position, but can see all of the sky over a period of six months.

Optics

thumb|upright=1.0|right|Engineers [[Carbon dioxide cleaning|cleaning a test mirror with carbon dioxide snow, 2015]]

thumb|upright=1.0|right|Main mirror assembly from the front with primary mirrors attached, November 2016

thumb|right|[[Diffraction spikes due to mirror segments and spider color-coded]]

Webb's primary mirror is a -diameter gold-coated beryllium reflector with a collecting area of . If it had been designed as a single, large mirror, it would have been too large for existing launch vehicles. The mirror is therefore composed of 18 hexagonal segments (a technique pioneered by Guido Horn d'Arturo), which unfolded after the telescope was launched. Image plane wavefront sensing via phase retrieval is used to position the mirror segments at the correct locations using precise actuators. After this initial configuration, they only need occasional updates every few days to maintain optimal focus. This is unlike terrestrial telescopes, for example the Keck telescopes, which must continually adjust their mirror segments using active optics to overcome the effects of gravitational and wind loading. The Webb telescope uses 132 small actuation motors to position and adjust the optics. The actuators can position the mirror with 10&nbsp;nanometer accuracy. which makes use of curved secondary and tertiary mirrors to deliver images that are free from optical aberrations over a wide field. The secondary mirror is in diameter. In addition, there is a fine steering mirror which can adjust its position many times per second to provide image stabilization. Point light sources in images taken by Webb have six diffraction spikes plus two fainter ones, due to the hexagonal shape of the primary mirror segments.

Scientific instruments

thumb|upright=1.0|right|NIRCam wrapped up in 2013

thumb|upright=1.0|right|The Calibration Assembly, one component of the NIRSpec instrument

thumb|upright=1.0|right|MIRI

The Integrated Science Instrument Module (ISIM) is a framework that provides electrical power, computing resources, cooling capability, and structural stability to the Webb telescope. It is made with a bonded graphite-epoxy composite attached to the underside of Webb's telescope structure. The ISIM holds the four science instruments and a guide camera. There are 10 sensors each of 4 megapixels. NIRCam serves as the observatory's wavefront sensor, required for wavefront sensing and control activities that align and focus the main mirror segments. NIRCam was built by a team led by the University of Arizona, with principal investigator Marcia J. Rieke.

  • NIRSpec (Near Infrared Spectrograph) performs spectroscopy over the same wavelength range. It was built by the European Space Agency (ESA) at ESTEC in Noordwijk, Netherlands. The leading development team includes members from Airbus Defence and Space in Ottobrunn and Friedrichshafen, Germany, and the Goddard Space Flight Center, with Pierre Ferruit (École normale supérieure de Lyon) as NIRSpec project scientist. The NIRSpec design provides three observing modes: a low-resolution prism mode, an R~1000 multi-object mode, and an R~2700 integral-field unit or long-slit spectroscopy mode. Mode switching is performed by operating a wavelength preselection mechanism, the Filter Wheel Assembly, and selecting a corresponding dispersive element (prism or grating) using the Grating Wheel Assembly. Both mechanisms are based on the successful ISOPHOT wheel mechanisms of the Infrared Space Observatory. The multi-object mode relies on a complex microshutter mechanism to enable simultaneous observations of hundreds of individual objects across NIRSpec's field of view. There are two sensors, each of 4 megapixels.
  • MIRI (Mid-Infrared Instrument) measures the mid-to-long-infrared wavelength range from 5 to 27&nbsp;μm. It contains both a mid-infrared camera and an imaging spectrometer. MIRI was developed as a collaboration between NASA and a consortium of European countries, and is led by George Rieke (University of Arizona) and Gillian Wright (UK Astronomy Technology Centre, Edinburgh, Scotland).
  • FGS/NIRISS (Fine Guidance Sensor and Near Infrared Imager and Slitless Spectrograph), led by the Canadian Space Agency (CSA) under project scientist John Hutchings (Herzberg Astronomy and Astrophysics Research Centre), is used to stabilize the line-of-sight of the observatory during science observations. Measurements from the FGS are used both to control the spacecraft's overall orientation and to drive the fine steering mirror for image stabilization. The CSA also provided a Near Infrared Imager and Slitless Spectrograph (NIRISS) module for astronomical imaging and spectroscopy in the 0.8 to 5&nbsp;μm wavelength range, led by principal investigator René Doyon at the Université de Montréal.

NIRCam and MIRI feature starlight-blocking coronagraphs for observation of faint targets such as extrasolar planets and circumstellar disks very close to bright stars. Along with the sunshield, it forms the spacecraft element of the space telescope. The spacecraft bus is on the Sun-facing "warm" side of the sunshield and operates at a temperature of about . The assembly was completed in California in 2015. It was integrated with the rest of the space telescope, leading to its 2021 launch. The spacecraft bus can rotate the telescope with pointing precision of one arcsecond and isolates vibration to 2 milliarcseconds.

Webb has two pairs of rocket engines (one pair for redundancy) to make course corrections on the way to L<sub>2</sub> and for station keepingmaintaining the correct position in the halo orbit. Eight smaller thrusters are used for attitude controlthe correct pointing of the spacecraft. The engines use hydrazine fuel ( at launch) and dinitrogen tetroxide as oxidizer ( at launch).

Servicing

Webb is not intended to be serviced in space. A crewed mission to repair or upgrade the observatory, as was done for Hubble, would not be possible, and according to NASA Associate Administrator Thomas Zurbuchen, despite best efforts, an uncrewed remote mission was found to be beyond available technology at the time Webb was designed. During the long Webb testing period, NASA officials referred to the idea of a servicing mission, but no plans were announced. Since the successful launch, NASA has stated that nevertheless limited accommodation was made to facilitate future servicing missions. These accommodations included precise guidance markers in the form of crosses on the surface of Webb, for use by remote servicing missions, as well as refillable fuel tanks, removable heat protectors, and accessible attachment points.

Comparison with other telescopes

thumb|upright=1.0|right|Comparison with the [[Hubble Space Telescope primary mirror]]

thumb|upright=1.0|right|Primary mirror size comparison between Webb and Hubble

The desire for a large infrared space telescope is decades old. In the United States, the Space Infrared Telescope Facility (later called the Spitzer Space Telescope) was planned while the Space Shuttle was in development, and the potential for infrared astronomy was acknowledged at that time. Unlike ground telescopes, space observatories are free from atmospheric absorption of infrared light. Space observatories opened a "new sky" for astronomers.

However, there is a challenge in the design of infrared telescopes: they must remain extremely cold, and the longer the wavelength of infrared light, the colder they must be. If not, the device's background heat overwhelms the detectors, effectively rendering it blind. This can be overcome by careful design. One method is to put the key instruments in a dewar with an icy substance, such as liquid helium. The coolant will slowly vaporize, limiting the instrument's lifetime to as short as a few months or as long as a few years.

It is also possible to maintain a low temperature by designing the spacecraft to enable near-infrared observations without coolant, as with the extended missions of the Spitzer Space Telescope and the Wide-field Infrared Survey Explorer, which operated at reduced capacity after coolant depletion. Another example is Hubble's Near Infrared Camera and Multi-Object Spectrometer (NICMOS) instrument, which started out using a block of nitrogen ice that depleted after a couple of years, but was then replaced during the STS-109 servicing mission with a cryocooler that worked continuously. The Webb Space Telescope is designed to cool itself without a dewar, using a combination of sunshields and radiators, with the mid-infrared instrument using an additional cryocooler.

{| class=wikitable style="margin:10px; text-align:center;"

|-

|+ Selected space telescopes and instruments

|-

! Name

! Launch year !! Wavelength <br />(μm) !! Aperture <br />(m)

! Cooling

|-

| Spacelab Infrared Telescope (IRT)

| 1985 || 1.7–118 || 0.15

| Helium

|-

| Infrared Space Observatory (ISO)

| 1995 || 2.5–240 || 0.60

| Helium

|-

| style="max-width:250px;" | Hubble Space Telescope Imaging Spectrograph (STIS)

| 1997 || 0.115–1.03 || 2.4

| Passive

|-

| style="max-width:250px;" | Hubble Near Infrared Camera and Multi-Object Spectrometer (NICMOS)

| 1997 || 0.8–2.4 || 2.4

| Nitrogen, later cryocooler

|-

| Spitzer Space Telescope

| 2003 || 3–180 || 0.85

| Helium

|-

| Hubble Wide Field Camera 3 (WFC3)

| 2009 || 0.2–1.7 || 2.4

| Passive and thermo-electric

|-

| Herschel Space Observatory

| 2009 || 55–672 || 3.5

| Helium

|-

| James Webb Space Telescope

| 2021 || 0.6–28.5 || 6.5

| Passive and cryocooler (MIRI)

|}

Webb's delays and cost increases have been compared to those of its predecessor, the Hubble Space Telescope. When Hubble formally began in 1972, it had an estimated development cost of US$300 million (), but by the time it was launched in 1990, the cost was about four times that. In addition, new instruments and servicing missions increased the price to at least US$9 billion by 2006

|-

| 2002 || Proposed project renamed James Webb Space Telescope, (mirror size reduced to 6 m)

|-

| 2003 || Northrop Grumman awarded contract to build telescope

|-

| 2007 || Memorandum of Understanding signed between NASA and ESA

|-

| 2010 || Mission Critical Design Review (MCDR) passed

|-

| 2011 || Proposed cancellation

|-

| 2016 || Final assembly completed

|-

| 25 Dec 2021 || Launch

|}

Discussions of a Hubble follow-on started in the 1980s, but serious planning began in the early 1990s. The Hi-Z telescope concept was developed between 1989 and 1994: a fully baffled aperture infrared telescope that would recede to an orbit at 3 astronomical unit (AU). This distant orbit would have benefited from reduced light noise from zodiacal dust.

Correcting the flawed optics of the Hubble Space Telescope (HST) in its first years played a significant role in the birth of Webb. In 1993, NASA conducted STS-61, the Space Shuttle mission that replaced HST's camera and installed a retrofit for its imaging spectrograph to compensate for the spherical aberration in its primary mirror.

The HST & Beyond Committee was formed in 1994 "to study possible missions and programs for optical-ultraviolet astronomy in space for the first decades of the 21st century". Emboldened by HST's success, its 1996 report explored the concept of a larger and much colder, infrared-sensitive telescope that could reach back in cosmic time to the birth of the first galaxies. This high-priority science goal was beyond the HST's capability because, as a warm telescope, it is blinded by infrared emission from its own optical system. In addition to recommendations to extend the HST mission to 2005 and to develop technologies for finding planets around other stars, NASA embraced the chief recommendation of HST & Beyond for a large, cold space telescope (radiatively cooled far below 0&nbsp;°C), and began the planning process for the future Webb telescope.

Preparation for the 2000 Astronomy and Astrophysics Decadal Survey (a literature review produced by the United States National Research Council that includes identifying research priorities and making recommendations for the upcoming decade) included further development of the scientific program for what became known as the Next Generation Space Telescope, and advancements in relevant technologies by NASA. As it matured, studying the birth of galaxies in the young universe and searching for planets around other starsthe prime goals coalesced into "Origins" by HST & Beyond becoming prominent.

An administrator of NASA, Dan Goldin, coined the phrase "faster, better, cheaper", and opted for the next big paradigm shift for astronomy, namely, breaking the barrier of a single mirror. That meant going from "eliminate moving parts" to "learn to live with moving parts" (e.g., segmented optics). Seeking to reduce the mirror mass by a factor of 10, beryllium was selected as the mirror substrate because the metal is low density (1.845 g/cm<sup>3</sup>), exceptionally stiff, and maintains a stable shape at cryogenic temperatures.

The mid-1990s era of "faster, better, cheaper" produced the NGST concept, with an aperture to be flown to , roughly estimated to cost US$500 million. In 1997, NASA worked with the Goddard Space Flight Center, Ball Aerospace & Technologies, and TRW to conduct technical requirement and cost studies of the three different concepts, and in 1999 selected Lockheed Martin and TRW for preliminary concept studies. Launch was at that time planned for 2007, but the launch date was pushed back many times (see table further down).

In 2002, the project was renamed after NASA's second administrator (1961–1968), James E. Webb (1906–1992). Webb led the agency during the Apollo program and established scientific research as a core NASA activity.

In 2003, NASA awarded TRW the US$824.8 million prime contract for the Webb telescope. The design called for a de-scoped primary mirror and a launch date of 2010. Later that year, TRW was acquired by Northrop Grumman in a hostile bid and became Northrop Grumman Space Technology. while Ball Aerospace & Technologies was subcontracted to develop and build the OTE itself, and the Integrated Science Instrument Module (ISIM).

Cost growth revealed in spring 2005 led to a re-planning in August 2005.

In the 2005 re-plan, the project's life-cycle cost was estimated at US$4.5 billion. This comprised approximately US$3.5 billion for design, development, launch, and commissioning, and approximately US$1.0 billion for ten years of operations. The ESA agreed in 2004 to contributing about €300 million, including the launch. The CSA pledged CA$39 million in 2007 and in 2012 delivered its contributions in equipment to point the telescope and detect atmospheric conditions on distant planets.

Detailed design and construction (2007–2021)

In January 2007, nine of the ten technology development items in the project successfully passed a Non-Advocate Review. These technologies were deemed sufficiently mature to mitigate significant risks in the project. The remaining technology development item (the MIRI cryocooler) completed its technology maturation milestone in April 2007. This technology review represented the beginning step in the process that ultimately moved the project into its detailed design phase (Phase C). By May 2007, costs were still on target. In March 2008, the project completed its Preliminary Design Review (PDR). In April 2008, the project passed the Non-Advocate Review. Other past reviews include the Integrated Science Instrument Module review in March 2009, the Optical Telescope Element review completed in October 2009, and the Sunshield review completed in January 2010.

In April 2010, the telescope passed the technical portion of its Mission Critical Design Review (MCDR). Passing the MCDR signified that the integrated observatory could meet all science and engineering requirements for its mission. The MCDR encompassed all previous design reviews. The project schedule underwent review during the months following the MCDR through the Independent Comprehensive Review Panel, which led to a re-plan of the mission aiming for a 2015 launch, but it was not until 2018. By 2010, cost overruns were impacting other projects, though Webb itself remained on schedule.

By 2011, the Webb project was in the final design and fabrication phase (Phase C).

Assembly of the hexagonal segments of the primary mirror, which was done via robotic arm, began in November 2015 and was completed on 3 February 2016. The secondary mirror was installed on 3 March 2016. Final construction of the Webb telescope was completed in November 2016, after which extensive testing procedures began.

In March 2018, NASA delayed Webb's launch by an additional 2 years to May 2020 after the telescope's sunshield ripped during a practice deployment, and its cables did not sufficiently tighten. In June 2018, NASA delayed the launch by an additional 10 months to March 2021, based on the independent review board's assessment following the failed March 2018 test deployment. The review identified that Webb launch and deployment had 344 potential single-point failures – tasks that had no alternative or means of recovery if unsuccessful, and therefore had to succeed for the telescope to work. In August 2019, the mechanical integration of the telescope was completed, something that was scheduled to be done 12 years before in 2007.

After construction was completed, Webb underwent final tests at Northrop Grumman's historic Space Park in Redondo Beach, California. A ship carrying the telescope left California on 26 September 2021, passed through the Panama Canal, and arrived in French Guiana on 12 October 2021.

Cost and schedule issues <span class="anchor" id="Time, budget"></span>

NASA's lifetime cost for the project is expected to be US$9.7 billion, of which US$8.8 billion was spent on spacecraft design and development, and US$861 million is planned to support five years of mission operations. Representatives from ESA and CSA stated their project contributions amount to approximately €700&nbsp;million and CA$200 million, respectively.

A 1984 study by the Space Science Board estimated that building a next-generation infrared observatory in orbit would cost US$4 billion (US$7B in 2006 dollars, or US$ 10B in 2020 dollars).|| 1 || 1.8 || 2.5 || 2.5

|-

| 2005 || 2013 || 3

|-

| 2006 || 2014 || 4.5

|-

|colspan=3 style="text-align:center"|2008: Preliminary Design Review

|-

| 2008 || 2014 || 5.1

|-

|colspan=3 style="text-align:center"|2010: Critical Design Review

|-

| 2010 || 2015 to 2016 || 6.5

|-

| 2017 || 2019 || 8.8

|-

| 2018 || 2020 || ≥8.8

|-

| 2019 || March 2021 || 9.66

|-

| 2021 || Dec 2021 || 9.70

|}

By 2008, when the project entered preliminary design review and was formally confirmed for construction, over US$1 billion had already been spent on developing the telescope, and the total budget was estimated at US$5 billion (equivalent to $&nbsp;billion in ). In summer 2010, the mission passed its Critical Design Review (CDR) with excellent grades on all technical matters. Still, schedule and cost slips at that time prompted Maryland U.S. Senator Barbara Mikulski to call for an external review of the project. The Independent Comprehensive Review Panel (ICRP), chaired by J. Casani (JPL), found that the earliest possible launch date was late 2015, at an additional cost of US$1.5 billion (bringing the total to US$6.5 billion). They also noted that this would have required additional funding in FY2011 and FY2012, and that a later launch date would result in a higher total cost.

On 6 July 2011, the United States House of Representatives' appropriations committee on Commerce, Justice, and Science moved to cancel the James Webb project by proposing an FY2012 budget that removed US$1.9 billion from NASA's overall budget, of which roughly one quarter was for Webb. US$3 billion had been spent and 75% of its hardware was in production. This budget proposal was approved by subcommittee vote the following day. The committee charged that the project was "billions of dollars over budget and plagued by poor management". as did Senator Mikulski. A number of editorials supporting Webb appeared in the international press during 2011 as well. In November 2011, Congress reversed plans to cancel Webb and instead capped additional funding to complete the project at US$8 billion.

While similar issues had affected other major NASA projects such as the Hubble telescope, some scientists expressed concerns about growing costs and schedule delays for the Webb telescope, worrying that its budget might be competing with those of other space science programs. A 2010 Nature article described Webb as "the telescope that ate astronomy". NASA continued to defend the budget and timeline of the program to Congress.

In 2018, Gregory L. Robinson was appointed as the new director of the Webb program. Robinson was credited with raising the program's schedule efficiency (how many measures were completed on time) from 50% to 95%.

On 27 March 2018, NASA pushed back the launch to May 2020 or later, In 2019, its mission cost cap was increased by US$800 million. After launch windows were paused in 2020 due to the COVID-19 pandemic, Webb was launched at the end of 2021, with a total cost of just under US$10 billion.

No single area drove the cost. For future large telescopes, there are five major areas critical to controlling overall cost:

  • System complexity
  • Critical path and overhead
  • Verification challenges
  • Programmatic constraints
  • Early integration and test considerations

Partnership

NASA, ESA, and CSA have collaborated on the telescope since 1996. ESA's participation in construction and launch was approved by its members in 2003, and an agreement was signed between ESA and NASA in 2007. In exchange for full partnership, representation, and access to the observatory for its astronomers, ESA is providing the NIRSpec instrument, the Optical Bench Assembly of the MIRI instrument, an Ariane 5 ECA launcher, and a workforce to support operations. The CSA provided the Fine Guidance Sensor and the Near-Infrared Imager Slitless Spectrograph and workforce to support operations.

Several thousand scientists, engineers, and technicians spanning 15 countries have contributed to the build, test, and integration of Webb. A total of 258 companies, government agencies, and academic institutions participated in the pre-launch project; 142 from the United States, 104 from 12 European countries (including 21 from the U.K., 16 from France, 12 from Germany and 7 international), and 12 from Canada.

Participating countries:

Naming concerns

In 2002, NASA administrator (2001–2004) Sean O'Keefe decided to name the telescope after James E. Webb, the administrator of NASA from 1961 to 1968 during the Mercury, Gemini, and much of the Apollo programs. In 2022, NASA released a report of an investigation, based on an examination of more than 50,000 documents. The report found "no available evidence directly links Webb to any actions or follow-up related to the firing of individuals for their sexual orientation", either in his time in the State Department or at NASA.

Mission goals

The James Webb Space Telescope has four key goals:

  • to search for light from the first stars and galaxies that formed in the universe after the Big Bang
  • to study galaxy formation and evolution
  • to understand star formation and planet formation
  • to study planetary systems and the origins of life

These goals can be achieved more effectively through near-infrared observation rather than in the visible spectrum. For this reason, Webb's instruments will not measure visible or ultraviolet light like the Hubble Telescope, but will have a much greater capacity to perform infrared astronomy. Webb will be sensitive to a range of wavelengths from 0.6 to 28&nbsp;μm (corresponding respectively to orange light and deep infrared radiation at about ).

Webb may be used to gather information on the dimming of the star KIC 8462852, which was discovered in 2015 and shows some abnormal light-curve properties.

Additionally, it will be able to tell if an exoplanet has methane in its atmosphere, allowing astronomers to determine whether or not the methane is a biosignature.

Orbit design

thumb|upright=1.4|right|Webb is not exactly at the point, but circles around it in a [[halo orbit.]]

thumb|upright=1.4|right|Alternative [[Hubble Space Telescope views of the Carina Nebula, comparing ultraviolet and visible (top) and infrared (bottom) astronomy. Far more stars are visible in the latter.]]

Webb orbits the Sun near the second Lagrange point () of the Sun–Earth system, which is farther from the Sun than the Earth's orbit, and about four times farther than the Moon's orbit. Usually, an object circling the Sun farther out than Earth would take longer than one year to complete its orbit. But near the point, the combined gravitational pull of the Earth and the Sun allows a spacecraft to orbit the Sun in the same time it takes the Earth to orbit the Sun. Staying close to Earth allows much higher data rates for a given antenna size.

The telescope circles about the Sun–Earth point in a halo orbit, which is inclined with respect to the ecliptic, has a radius varying between about and , and takes about half a year to complete. This requires some station-keeping: around per year from the total ∆v budget of . Two sets of thrusters constitute the observatory's propulsion system. Because the thrusters are located solely on the Sun-facing side of the observatory, all station-keeping operations are designed to slightly undershoot the required amount of thrust in order to avoid pushing Webb beyond the semi-stable point, a situation which would be unrecoverable. Randy Kimble, the Integration and Test Project Scientist for the JWST, compared the precise station-keeping of Webb to "Sisyphus [...] rolling this rock up the gentle slope near the top of the hill – we never want it to roll over the crest and get away from him".

Infrared astronomy

thumb|upright=1.4|right|Infrared observations can see objects hidden in visible light, such as the [[HUDF-JD2 shown here.]]

thumb|upright=1.6|right|Atmospheric windows in the infrared: Much of this type of light is blocked when viewed from the Earth's surface. It would be like looking at a rainbow but only seeing one color.

Webb is the formal successor to the Hubble Space Telescope (HST), and since its primary emphasis is on infrared astronomy, it is also a successor to the Spitzer Space Telescope. Webb will far surpass both those telescopes, enabling it to see many more, and much older, stars and galaxies. Observing in the infrared spectrum is a key technique for achieving this, because of cosmological redshift, and because it better penetrates obscuring dust and gas. This allows observation of dimmer, cooler objects. Since water vapor and carbon dioxide in Earth's atmosphere strongly absorb most infrared radiation, ground-based infrared astronomy is limited to narrow wavelength ranges where the atmosphere absorbs less strongly. Additionally, the atmosphere itself radiates in the infrared, often overwhelming the light from the observed object. This makes a space telescope preferable for infrared observation.

The more distant an object is, the younger it appears; its light has taken longer to reach human observers. Because the universe is expanding, as light travels, it becomes redshifted, and objects at great distances are therefore easier to see in the infrared.

Infrared radiation can pass more freely through regions of cosmic dust that scatter visible light. Observations in infrared allow the study of objects and regions of space which would be obscured by gas and dust in the visible spectrum, such as the molecular clouds where stars are born, the circumstellar disks that give rise to planets, and the cores of active galaxies. Spitzer showed the importance of mid-infrared, which is helpful for tasks such as observing dust disks around stars. In this capacity, STScI was to be responsible for the scientific operation of the telescope and delivery of data products to the astronomical community. Data was to be transmitted from Webb to the ground via the NASA Deep Space Network, processed and calibrated at STScI, and then distributed online to astronomers worldwide. As with Hubble, anyone, anywhere in the world, will be allowed to submit proposals for observations. Each year, several astronomy committees will peer review submitted proposals to select the projects to observe the following year. The authors of the selected proposals will typically have 1 year of private access to the new observations, after which the data will become publicly available for download from the STScI online archive.

The bandwidth and digital throughput of the satellite are designed to operate at 458 gigabits of data per day for the length of the mission (equivalent to a sustained rate of 5.42 Mbps). The digitization of the analog data from the instruments is performed by the custom SIDECAR ASIC (System for Image Digitization, Enhancement, Control And Retrieval Application Specific Integrated Circuit). NASA stated that the SIDECAR ASIC will include all the functions of a instrument box in a package and consume only 11&nbsp;milliwatts of power. Since this conversion must be done close to the detectors, on the cold side of the telescope, the low power dissipation is crucial for maintaining the low temperature required for optimal operation of Webb.

Micrometeoroid strikes

The C3 mirror segment suffered a micrometeoroid strike from a large dust mote-sized particle between 23 and 25 May 2022, the fifth and largest strike since launch, reported 8 June 2022, which required engineers to compensate for the strike using a mirror actuator. Despite the strike, a NASA characterization report states "all JWST observing modes have been reviewed and confirmed to be ready for science use" as of 10 July 2022.