The Extremely Large Telescope (ELT) is an astronomical observatory under construction. When completed, it will be the world's largest optical and mid-infrared extremely large telescope. Part of the European Southern Observatory (ESO) agency, it is located on top of Cerro Armazones in the Atacama Desert of northern Chile, 23 km from the existing facilities at Paranal Observatory.
The design consists of a reflecting telescope with a segmented primary mirror and a diameter secondary mirror. The telescope is equipped with adaptive optics, six laser guide star units, and various large-scale scientific instruments.
The project was originally called the European Extremely Large Telescope (E-ELT), but the name was shortened in 2017. The ELT is intended to advance astrophysical knowledge by enabling detailed studies of planets around other stars, the first galaxies in the Universe, supermassive black holes, the nature of the Universe's dark sector, and to detect water and organic molecules in protoplanetary disks around other stars.
On 11 June 2012, the ESO Council approved the ELT programme's plans to begin civil works at the telescope site, with the construction of the telescope itself pending final agreement with governments of some member states.]]
thumb|upright=1.1|ELT construction status in November 2025
On 26 April 2010, the European Southern Observatory (ESO) Council selected Cerro Armazones, Chile, as the baseline site for the planned ELT.
Early designs included a segmented primary mirror with a diameter of and an area of about , with a secondary mirror with a diameter of . However, in 2011 a proposal was put forward to reduce overall size by 13% to 978 m<sup>2</sup>, with a diameter primary mirror and a diameter secondary mirror. The project received preliminary approval in June 2012. In 2014, the start of operations was planned for 2024. and a technical first light is planned for March 2029. The telescope underwent a Phase B study in 2014 that included "contracts with industry to design and manufacture prototypes of key elements like the primary mirror segments, the adaptive fourth mirror or the mechanical structure (...) [and] concept studies for eight instruments".
Design
thumb|upright=1.1|Schematic view of the ELT
thumb|upright=1.1|The optical system of the ELT showing the location of the mirrors
thumb|upright=1.1|Cast of the first ELT main mirror segments
thumb|upright=1.1|Several segments of the primary mirror
thumb|upright=1.1|ELT's M2 mirror blank
The ELT will use a novel design with a total of five mirrors. The first three mirrors are curved (non-spherical) and form a three-mirror anastigmat design for excellent image quality over the 10-arcminute field of view (one-third of the width of the full Moon). The fourth and fifth mirrors are flat, and respectively provide adaptive optics correction for atmospheric distortions (mirror 4) and tip-tilt correction for image stabilization (mirror 5). The fourth and fifth mirrors also send the light sideways to one of two Nasmyth focal stations at either side of the telescope structure, allowing multiple large instruments to be mounted simultaneously.
Primary mirror
The primary mirror will be composed of 798 hexagonal segments, each approximately across and with a thickness of . Two segments will be re-coated and replaced each working day, to keep the mirror always clean and highly reflective.
Edge sensors constantly measure the positions of the primary mirror segments relative to their immediate neighbours. 2394 position actuators (3 for each segment) use this information to adjust the system, keeping the overall surface shape unchanged against deformations caused by external factors such as wind, gravity, temperature changes and vibrations.
In January 2017, and German company Micro-Epsilon. These sensors can measure relative positions to an accuracy of a few nanometres, the most accurate ever used in a telescope.
In May 2017, ESO awarded two additional contracts for the segments of the primary mirror. One was awarded to the German company Schott AG who manufactures the blanks of the 798 segments, as well as a maintenance set of 133 additional segments, one for each unique segment shape in the surface. Once the ELT is in operation, the maintenance set allows segments to be removed, replaced, and recoated on a rotating basis without leaving temporary gaps in the surface. The segments were cast from the same low-expansion ceramic Zerodur as the existing Very Large Telescope mirrors in Chile.
The other segment contract was awarded to the French company, Safran Reosc, a subsidiary of Safran Electronics & Defense. They receive the mirror blanks from Schott, and polish one mirror segment per day to meet the 7-year deadline. During this process, each segment is polished until it has no surface irregularity greater than 7.5 nm root mean square. Afterward, Safran Reosc mounts, tests, and completes all optical testing before delivery. This is the second-largest contract for ELT construction and the third-largest contract ESO has ever signed.
The segment support system units for the primary mirror were designed and are produced by CESA (Spain) and VDL (the Netherlands). The contracts signed with ESO also include the delivery of detailed and complete instructions and engineering drawings for their production. Additionally, they include the development of the procedures required to integrate the supports with the ELT glass segments; to handle and transport the segment assemblies; and to operate and maintain them.
As of July 2023, over 70% of the mirror segment blanks and their supporting structures had been manufactured,
Secondary mirror
Making the secondary mirror is a major challenge as it is highly convex, and aspheric. It is also very large; at in diameter and weighing , it will be the largest secondary mirror ever employed on an optical telescope and the largest convex mirror ever produced.
In January 2017, Schott AG was also awarded the contract for the much larger primary segment of the mirror.
Complex support cells are also necessary to ensure the flexible secondary and tertiary mirrors retain their correct shape and position; these support cells will be provided by SENER. Like the tertiary mirror, the secondary mirror will be mounted on 32 points, with 14 along its edges and 18 on the back. The entire assembly will be mounted on a hexapod, allowing its position to be aligned every few minutes to sub-micrometer precision. Deformations on the secondary mirror have a much smaller effect on the final image compared to errors on the tertiary, quaternary, or quinary mirrors.
As of July 2023, the tertiary mirror had been cast and was being polished. consists of six component petals, control systems, and voice-coil actuators. The image distortion caused by the turbulence of the Earth's atmosphere can be corrected in real-time, as well as deformations caused by the wind upon the main telescope. The ELT's adaptive optics system will provide an improvement of about a factor of 500 in the resolution compared to the best seeing conditions achieved so far without adaptive optics. partnered with INAF (Istituto Nazionale di Astrofisica) as subcontractors, are responsible for the design and manufacture of the quaternary mirror. The 6 petals were cast by Schott in Germany and polished by Safran Reosc.
As of July 2023, all six petals were completed and in the process of being integrated into their support structure.
As of early 2024 the six component petals had been fabricated and are being brazed into a single unit.
At the very bottom, on top of the foundation, is a vibration and seismic isolation layer. This consists of rubber isolation bearings, springs, and a locking system for larger seismic events. On top of this is the large concrete block (the pier) on which the telescope rests. This differs from most large telescopes where the isolation is between the pier and the telescope. This gives an unusually large seismic mass of 20,000 tonnes, which helps with seismic isolation, avoids mount resonances, and limits seismic acceleration imparted to instrumentation on the telescope.
On top of the concrete pier are the azimuth tracks. On top of them sits the azimuth structure, rotating around a vertical axis and supported by hydrostatic bearings. On top of that sits the altitude structure, which allows the telescope to tip from horizontal to vertical, and is also supported on hydrostatic bearings. The rotating mass is about 3,700 tonnes, and can track at degrees/second in azimuth and degrees/second in elevation.
Both azimuth and elevation angles need to be measured and controlled extremely accurately. Therefore each axis contains an optical tape readout and direct drive electrical motors. Both systems are redundant for increased availability.
Within the elevation assembly, there is a complex system of active mirror supports, designed to hold the 5 main mirrors in proper shape and alignment, despite environmental influences and changes in orientation. This system also supports the optics needed to launch, and receive, the laser guide stars that are used to correct for atmospheric distortion using the adaptive optics of mirror M4.
Dome
thumb|upright=1.2|ELT conceptthumb|upright=1.1|ELT compared to the [[Very Large Telescope|VLT and the Colosseum]]
The ELT dome has a height of from the ground and a diameter of , making it the largest dome ever built for a telescope. The dome has a total mass of around , and the telescope mounting and tube structure has a total moving mass of around .
For the observing slit, the dome is equipped with a single pair of large sliding doors. This pair of doors allows an opening of .
ESO signed a contract for its construction, together with the main structure of the telescopes, with the Italian ACe Consortium, consisting of Astaldi and Cimolai and the nominated subcontractor, Italy's EIE Group. The signature ceremony took place on 25 May 2016 at ESO's Headquarters in Garching bei München, Germany.
The dome is to provide needed protection to the telescope in inclement weather and during the day. A number of concepts for the dome were evaluated. The final design is a nearly hemispherical dome, rotating atop a concrete pier, with curved laterally-opening doors. This is a re-optimisation from the previous design, aimed at reducing cost.
One year after signing the contract, and after the laying of the first stone ceremony in May 2017, the site was handed over to ACe, signifying the beginning of the construction of the dome's main structure. As of April 2025, the dome was complete and the doors were in the process of installation.
Astronomical performance
In terms of astronomical performance the dome is required to be able to track about the 1-degree zenithal avoidance locus as well as preset to a new target within 5 minutes. This requires the dome to be able to accelerate and move at angular speeds of 2 degrees/s (the linear speed is approximately , equivalent to a fast walk). The dome is designed to allow complete freedom to the telescope so that it can position itself whether it is opened or closed. It will also permit observations from the zenith down to 20 degrees from the horizon.
Windscreen
With such a large opening, the ELT dome requires the presence of a windscreen to protect the telescope's mirrors (apart from the secondary), from direct exposure to the wind. The design of the windscreen minimises the volume required to house it. Four spherical blades, spanning the width of the opening, can be raised and lowered in front of the telescope aperture to restrict the wind.
Ventilation and air-conditioning
The dome design ensures that the dome provides sufficient ventilation for the telescope not to be limited by dome seeing. For this the dome is also equipped with louvers, whereby the windscreen is designed to allow them to fulfill their function.
Computational fluid dynamic simulations and wind tunnel work are being carried out to study the airflow in and around the dome, as well as the effectiveness of the dome and windscreen in protecting the telescope.
Besides being designed for water-tightness, air-tightness is also one of the requirements as it is critical to minimise the day-time air-conditioning load. The air-conditioning of the dome is necessary not only to thermally prepare the telescope for the forthcoming night but also in order to keep the telescope optics clean.
The air-conditioning of the telescope during the day is critical and the current specifications permit the dome to cool the telescope and internal volume by over 12 hours.
Science goals
thumb|upright=1.1|The official trailer for the ELT showing the preliminary design.
The ELT will search for extrasolar planets—planets orbiting other stars. This will include not only the discovery of planets down to Earth-like masses through indirect measurements of the wobbling motion of stars perturbed by the planets that orbit them, but also the direct imaging of larger planets and possibly even the characterisation of their atmospheres. The telescope will attempt to image Earth-like exoplanets.
By probing the most distant objects the ELT will provide clues to understanding the formation of the first objects that formed: primordial stars, primordial galaxies and black holes and their relationships. Studies of extreme objects like black holes will benefit from the power of the ELT to gain more insight into time-dependent phenomena linked with the various processes at play around compact objects.]]
The telescope will have several scientific instruments and will be able to switch from one instrument to another within minutes. The telescope and dome will also be able to change positions on the sky and start a new session of observation in a short time.
Four of its instruments, the first generation, will be available at or shortly after first light, while two others will begin operations later. Throughout its operation other instruments can be installed.
The first generation includes four instruments: MICADO, HARMONI and METIS, along with the adaptive optics system MORFEO.
- HARMONI: The High Angular Resolution Monolithic Optical and Near-infrared Integral field spectrograph (HARMONI) will function as the telescope's workhorse instrument for spectroscopy.
- METIS: The Mid-infrared ELT Imager and Spectrograph (METIS) will be a mid-infrared imager and spectrograph.
- MICADO: The Multi-AO (adaptive optics) Imaging Camera for Deep Observations (MICADO) will be the first dedicated imaging camera for the ELT and will work with the Multiconjugate adaptive Optics Relay For ELT Observations, (MORFEO, formerly MAORY).
The second generation of instruments consists of MOSAIC and ANDES.
- MOSAIC: A proposed multi-object spectrograph which will allow astronomers to trace the growth of galaxies and the distribution of matter from shortly after the Big Bang to the present day.
- ANDES (formerly HIRES): The ArmazoNes high Dispersion Echelle Spectrograph will be used to search for indications of life on Earth-like exoplanets, find the first-born stars of the universe, test for possible variations of the fundamental constants of physics, and measure the acceleration of the Universe's expansion.
Comparison
One of the largest optical telescopes operating today is the Gran Telescopio Canarias, with a aperture and a light-collecting area of . Other planned extremely large telescopes include the Giant Magellan Telescope with a mirror diameter of and area of , and the Thirty Meter Telescope with a diameter of , and an area of . Both of these are also targeting the 2030s for completion. These two other telescopes roughly belong to the same next generation of optical ground-based telescopes. Each design is much larger than previous telescopes. The unaided human eye has an angular resolution of 1 arcminute which corresponds to separating two light sources 30 cm apart from 1 km distance.
thumb|upright=3.8|center|Size comparison between the ELT and other telescope domes
{| class="wikitable sortable" style="text-align: center;"
|-
! Name !! Aperture<br />diameter (m) !! Collecting<br />area (m²) !! First light !! Ref
|-
| align=left | Extremely Large Telescope (ELT) || 39 || 978 || 2029 ||
|-
| align=left | Large Binocular Telescope (LBT)
|2 x 8.4 (22.8)
|111
|2005
|
|-
| align=left | Southern African Large Telescope (SALT) || 11.1 × 9.8 || 79 || 2005 ||
|-
| align=left | Hobby–Eberly Telescope (HET)
|11.1 × 9.8
|79
|1996
|
|-
| align=left | Gran Telescopio Canarias (GTC) || 10.4 || 74 || 2007 ||
|-
| align=left | Keck Telescopes || 10.0 || 76 || 1990, 1996 ||
|-
| align=left | Very Large Telescope (VLT) || 8.2 || 50 (×4) || 1998–2000 ||
|-
| colspan=4 style="font-size: 0.85em; padding: 6px 0 4px 4px;" | Notes: Future first-light dates are provisional and likely to change.
|}
See also
- Lists of telescopes
- List of largest optical reflecting telescopes
- List of optical telescopes
- Large Binocular Telescope
- European Solar Telescope
- Gran Telescopio Canarias
- Overwhelmingly Large Telescope
- List of astronomical observatories
- List of highest astronomical observatories
- Other observatories in Chile:
- Llano de Chajnantor Observatory
- Atacama Large Millimeter Array
- Paranal Observatory
- Very Large Telescope
- Cerro Armazones Observatory
- La Silla Observatory
- Cerro Tololo Inter-American Observatory
References
External links
- ESO Extremely Large Telescope
- ESO The Extremely Large Telescope ("E-ELT") Project
- Final stage for telescope design
- Green light for ELT
- Ground Telescope to Super Size
- MICADO
- METIS
- HARMONI
- Record mirror for Euro telescope BBC Online August 7 2006
- ESO Council Gives Green Light to Detailed Study of the European Extremely Large Telescope Spaceref.com (via archive.today)